El Greco Waterline Rehabilitation

This project consists of replacing an existing six (6) inch water main with approximately 1,100 lineal feet of six (6) inch Ductile Iron pipe with restrained joints, fire hydrant, and 22 services.

  • Construction is tentatively scheduled to begin on April 1, 2019 and be complete in late June. This schedule is subject to change as conditions and weather can be somewhat unpredictable.
  • Work hours are Monday to Friday, 7 a.m. – 6 p.m.

Check back for project updates.