Skip to Main Content
Public Works Banner

Cervantes Emergency Water Line Repair

Project Background/Summary

Emergency roadway and utility repair and replacement caused by a water main break that occurred on Cervantes Street, August 30, 2013. Work will include extensive roadway reconstruction, waterline replacement, and potentially trench replacement for wastewater and stormwater facilities. Project not budgeted in the CIP, however, there is currently $230,000 available for waterline rehabilitation, undefined location.

If you would like more information about this project, please contact David Kudna, Project Manager at  email.

Updates

May 14, 2015

The City and the Contractor thank you for your patience and your cooperation during construction.  The project is ahead of schedule and nearing completion. 

  • Emery and Sons Construction Group has completed main line and service installations.
  • Permanent trench patch will be complete today.
  • Contractor will be installing the water main across the ravine today.
  • We anticipate the Contractor will rebuild the damaged sections of Cervantes next week.  Please do not park within the rebuild section, which starts roughly at 206 Cervantes and continues down to Jefferson Parkway.

April 8, 2015

  • Emery and Sons Construction Group will begin constructing the water main replacement starting Monday, April 10, 2015, which will include opening trenching in Cervantes.
  • The Contractor will post no-parking signs delineating the work zone
  • The Contractor will provide access to driveways within the work zone.

March 24, 2015

The Cervantes Water Main Replacement project is moving into the construction phase.

  • Sealed proposals were received for WO 187 - Cervantes Water Main Replacement Project for the City of Lake Oswego. Proposals were received by David Kudna, Project Manager, on February 18, 2015, 2:00 PM, local time. The apparent low bidder was Emery & Sons Construction Group.
  • The Lake Oswego City Council awarded the construction contract to Emery and Sons Construction Group on March 3, 2015.
  • The Contractor will begin mobilization the week of April 6th.
  • Typical construction hours  are Monday - Friday, 7:00 am to 6:00 pm.
  •  The project limits are from 335 Cervantes to the east connection with Jefferson Parkway.
  • Sections of Cervantes Road will be closed to through traffic during construction. Closures will be updated throughout project.  Please check back for updates.

 

Cervantes Image 1

ID

WO 187

Type

Capital Improvement Projects

Contact Us

David Kudna, Project Manager 503-534-5299

Status

Active