Skip to Main Content
City of Lake Oswego
Public Works Banner

Country Club Road Improvement Project (10th Street to Six Corners)

Project Background/Summary

In February 2017, the City of Lake Oswego hired a consultant team to develop Construction Plans and Specifications for utility and pavement improvements for a section of Country Club Road from 10th Street to Six Corners (intersection of Bayberry Road, Iron Mountain Road, Country Club Road, C Avenue).

While the Country Club Road pavement is in need of repair, all major utilities from 10th Street to Six Corners are beyond repair and need replacement or upgrading, prior to paving. Fire protection is also substandard in this section of Country Club Road and fire hydrants are required to bring it up to current Fire Code.

Project Description

The purpose of the Country Club Improvement Project (from 10th Street to Six Corners) is to rehabilitate the pavement, realign and upgrade a sewer main, update the stormwater system, and replace and upsize the water line to add fire protection. Please find a map of the project area attached.

To minimize impacts to neighbors and traffic, the utility and pavement improvements will be conducted in a single project from 10th Street to Six Corners. Combining the roadway work and utility improvements into a single project not only saves time and money, it also minimizes disruption to neighbors and the traveling public by avoiding multiple construction projects in the same section.

Any improvements or possible changes to the existing traffic pattern at Six Corners are not included in this project, and may be addressed in a future project.

At this time it is anticipated that design for the Country Club Road Improvement Project (from 10th Street to Six Corners) could be completed by early 2018, followed by construction beginning in spring of 2018 and finishing in fall of 2018.

Updates

August 10, 2017 – Additional Field Work & Lane Closures

On Monday, August 14, there will be intermittent westbound lane closures on Country Club Road (from Country Club Court to 10th Street) and on Country Club Court between 7 a.m. and 3 p.m. Crews will be conducting exploratory drilling in the right-of-way. Flaggers or signage will direct drivers or assist local neighbors with access. Please expect some delays during this work.

April 6, 2017 - Additional Lane Closures Week of April 10

On Monday, April 10 and Tuesday, April 11, there will be intermittent lane closures from 9 a.m. - 3 p.m. on Country Club Road between Six Corners and 10th Street. Crews will be collecting data, conducting exploratory drilling and inspecting existing sanitary sewer lines and laterals. Flaggers or signage will be in place to direct traffic - please expect some delays.

March 31, 2017 - Intermittent Lane Closures

On Monday, April 3, there will be intermittent lane closures from 9 a.m. - 3 p.m. on Country Club Road between Six Corners and 10th Street. Crews will be collecting data and inspecting existing sanitary sewer lines and laterals. Flaggers or signage will be in place to direct traffic - please expect some delays.

Survey work will also be taking place in the project area during the week of April 3, however no lane closures are anticipated during the survey work.

March 21, 2017 - Upcoming Field and Survey Work

Beginning in April, crews will be taking photos, surveying the project area, mapping and assessing the health of trees, conducting geotechnical investigations, and gathering other information to inform the preliminary design work and future construction.

During April, neighbors and the traveling public may notice the following:

  • Underground utilities will be marked with paint on the street, shoulder or in the grass, or in the public right-of-way. Marks will disappear overtime, but these are necessary to complete our survey for use in design and later construction.
     
  • Some lane closures will take place between 9 a.m. – 3 p.m., while crews collect data on existing conditions (i.e., CCTV utilities, surveying, exploratory borings, soil sampling), in the right-of-way; flaggers or signage will direct drivers or assist local neighbors with access. Please expect some minor delays during this work.
     
  • Trees may be tagged during the survey work for mapping purposes. We will be looking at how to minimize any impact to trees and will have an arborist working with the team.
     
  • Wooden stakes with flags will be left at some places along the project area. These may indicate public right-of-way, property lines, drainage issues or other considerations. Please don’t remove the stakes.

 

Other Materials

ID

WO 246

Type

Capital Improvement Projects

Contact Us

David Kudna, Project Manager
503-534-5299
e-mail

Summer 2017 Construction Projects Map

Construction Projects Map

Status

Active