Kerr Parkway Update

July 11, 2014

  • Kerr Parkway will remain closed between Jefferson Parkway and McNary Parkway (North Intersection) at least through next week.  This section has taken longer than anticipated due to some required design changes.
     
  • This week the contractor worked on a water main that will be relocated and began building the retaining wall. 
     
  • Next week the contractor is scheduled to install new curbs, sidewalk ramps, and the new waterline.